Why the roof comes first.
A solar plant stays on the roof for many years, usually more than 20. If the roof needs repair after installation, such as a leak or sheets that must be replaced, the panels above it are taken off and fitted again, and that part of the plant stands idle until the repair is finished.
That is why it is wise to know your roof's condition from the start, before the offer and before you sign. Start with six things to check; they tell you what to ask.
Six things that decide a roof's readiness.
- The building structure that carries the load. The steel members under the metal sheets (the purlins) and the building's frames, or the concrete slab.
- The roof covering and its condition. The metal sheets and their fixing points, or the waterproofing layer on the concrete.
- Sources of shade. The parapet, water tanks, air-conditioning units, chimneys and neighbouring buildings.
- Ladder and walkways. A safe ladder up and walkways for maintenance. Skylights (translucent roof sheets) must never be walked on.
- The cable route and the place of the inverter. A clear route for the cables, and a place for the inverter that is shaded, well ventilated and easy to reach.
- Drainage. Rainwater and the water used to clean the panels must find their way to the gutters and outlets.
Shade on a small part of the panels can cost more production than its size, which is why the sources of shade are identified from the start.
If your roof is sheet metal.
On a metal-sheet roof the load ends up on the purlins, the steel members the sheets are fixed to, and travels from them to the building's frames and columns. The sheet itself is a thin covering: it passes the load on to the purlins and can carry little itself, which is why its thickness and condition matter.
- The kind of sheet: thin, thick or sandwich panel. It decides the fixing method.
- Rust: it shows first around the fixing screws, where the sheets overlap and beside the gutters. Check it from a safe walkway or from below, because rusted sheets may not carry a person's weight. Sheets at the end of their life are replaced before installation.
- Keeping water out: every fixing point in the sheet is sealed with a watertight rubber gasket. Some kinds of sheet take clamps without any drilling.
- Sandwich panels: the outer layer is a thin sheet over a layer of thermal insulation. To keep the insulation intact, the fixing follows the panel maker's instructions or passes the load straight to the purlins. Ask what the insulation is made of before you sign, because some kinds can burn.
- Skylights: they do not carry a person's weight. Never walk on them; a good design keeps a distance around them.
If your roof is concrete.
A concrete slab usually carries more than a metal-sheet roof. But that is confirmed by a review of the building's structural drawings, not by eye.
- The waterproofing layer: find out its age and condition. If it is old or leaking, renewing it before installation is far easier than renewing it under the panels.
- The fixing method: concrete blocks that hold the mounting structure down by their weight, without drilling, or anchors in the slab that go through the waterproofing layer. The first weighs more; with the second, every point must be sealed.
- Drainage: the blocks must not obstruct the water's path to the outlets or leave water standing on the roof.
- The parapet: it casts shade, and its shadow is longer in winter. That is why the rows of panels keep a distance from it.
The load in plain words.
The panels and the mounting structure add a permanent weight to the roof. The wind also acts on them, so the mounting structure has to pass its force into the building, above all at the roof's edges and corners.
Mounting parallel to a metal-sheet roof usually adds about 12 to 15 kilograms on each square metre covered with panels. The actual figure varies with the type of panel and the mounting structure.
| Fixing method | Added weight | Ask about |
|---|---|---|
| Parallel to a metal-sheet roof | About 12 to 15 kilograms per square metre | How the load reaches the purlins, and how the fixing points are sealed |
| Concrete blocks | More; up to several times parallel mounting, depending on tilt and wind | The slab's load capacity, and protection of the waterproofing under the blocks |
| Anchors in the slab | Less than blocks | The kind and thickness of the slab, and how every drill hole is sealed |
What to prepare for your project file.
The technical survey comes after the contract, at the start of the execution. On site our team confirms the roof, the area, the cable routes and the place of the inverter, before the supply starts. So your offer and your contract are built on the information you prepare for your project file from the start.
- The roof's age, and when it was last repaired or its waterproofing renewed.
- The building's structural drawings, if they exist.
- Photos of the roof from each corner, taken from a safe place without walking on old sheets or skylights, and a photo of the building's structure from below if the roof is sheet metal.
- Known leaks, even if they have been repaired.
- Any work planned on the roof: new sheets, new waterproofing or equipment to be installed.
- What is on the roof: tanks, air-conditioning units, chimneys and skylights.
You can add the roof photos to your project file whenever it suits you, and write the rest in the notes field of the same file. Keep it at hand when you review your offer and before you sign.
And if the roof is not ready?
That is not the end of the project; it is a matter of order: repair first, then install.
- Sheets at the end of their life: they are replaced before installation, because replacing them later means taking the panels off.
- A leak that is still there: it is repaired, and you make sure it has stopped, before panels go on top of it.
- A building structure of unknown load capacity: the structural check comes first, and we carry it out; any strengthening is done before installation.
We do not install on fibre-cement (asbestos) roofs, which some older factories still have: they do not carry a person's weight, and drilling them releases harmful dust.
If the roof is not suitable or its area is not enough, and you have land beside the building, the plant can be built on a ground structure.
Ask before you sign: what work the roof needs, and who is responsible for it. Both should be clear in the offer and the contract, because the contract sets out your obligations and the site's readiness.
Related pages.
- The area a plant needsHow much area your plant takes, and why the figure changes from one surface to another.
- From area to capacityHow much plant your roof carries.
- How to compare solar offersSix fields in every offer, and the questions to ask each company.
- Safety: isolation and what to do in a fireWhere the isolation points are, what each one disconnects, and what to do in an emergency.
- Supply and installationIn stages we agree with you.